Data centers in Louisiana
1 project tracked, with 1 restriction in force. Updated 2026-09-07.
Projects tracked11 not cancelled or on hold
Under construction0or partially operational
IT load tracked300MWsum of disclosed critical IT load
Restrictions in force1see the ledger below
Every Louisiana project we track
Sorted by IT load. A blank capacity means the figure has not been disclosed, not that the project is small.
| Project | Location | IT load | Status | Developer | Target online | Source |
|---|---|---|---|---|---|---|
| Applied Digital Delta Forge 1 — BoyceDC-LA-0001 | Boyce | 300MW | Announced | Applied Digital | Mid-2027 initial operation; phased completion 2028 | Source ↗ |
By stage
Markets
- Central Louisiana1
Restrictions in force in Louisiana
Moratoriums, bans, zoning conditions and tax changes currently in effect. Which specific projects each one reaches is part of the subscription.
| Jurisdiction | Level | What it does | Window |
|---|---|---|---|
| New Orleans, LA1-yr data center moratorium | City / Town | Moratorium | Jan 2026 → Jan 2027 |
Developers and owners active in Louisiana
- Applied Digital