Data centers in Missouri
21 projects tracked, 5 building, with 18 restrictions in force. Updated Oct 22, 2026.
Projects tracked2121 active
Building5under construction, awaiting power, partially operational or expanding
IT load tracked2,306MWtotal IT load disclosed
Restrictions in force18see the ledger below
Grid, 115 kV and up1,115 lines279 substations · Sources: © OpenStreetMap contributors, HIFLD (2023)
Power plants, 50 MW and up65 operating13 planned generators · EIA-860M, 2026-07
The largest Missouri projects we track
The 3 largest of 21 by IT load. The rest are in the terminal.
| Project | Location | Status |
|---|---|---|
| Google Project Mica — Kansas City Northland | Kansas City | Under Construction |
| CRG Festus Data Center | Festus | Entitled |
| Cielo Kansas City Data Center | Jackson | Rumored |
and 18 more Missouri projects in the terminal · start the 7-day free trial
By stage
Markets
- St. Louis9
- Kansas City6
- Joplin / Southwest Missouri3
- Central Missouri2
- Northwest Missouri1
Restrictions in force in Missouri
Moratoriums, bans, zoning rules and tax changes in effect now. Which projects each one affects is part of the subscription.
| Jurisdiction | Level | What it does | Window |
|---|---|---|---|
| Ameren MissouriLarge Load Customer Service tariff, Schedule LLCS (PSC ET-2025-0184) | Utility / Grid | Large-Load / Interconnection Rule | Since Dec 2025 · no end date |
| City of Camdenton, MO1-yr data center moratorium | City / Town | Moratorium | May 2026 → May 2027 |
| City of Columbia, MOdata center moratorium | City / Town | Moratorium | Since May 2026 · no end date |
| City of Independence, MO6-mo data center moratorium | City / Town | Moratorium | Jul 2026 → Jan 2027 |
| City of Independence, MOdata center and BESS zoning standards | City / Town | Zoning Overlay / Special Use Permit | Since Oct 2026 · no end date |
| City of Marshfield, MOdata center definition and heavy-industrial conditional use | City / Town | Zoning Overlay / Special Use Permit | Since Apr 2026 · no end date |
| City of Neosho, MO1-yr data center moratorium | City / Town | Moratorium | Jul 2026 → Jul 2027 |
| City of Springfield, MO120-day data center moratorium | City / Town | Moratorium | Jun 2026 → Oct 2026 |
| City of St. Joseph, MO1-yr data center moratorium | City / Town | Moratorium | Jul 2026 → Jul 2027 |
| City of St. Louis, MOBoard Bill 49 data-center zoning overlay | City / Town | Zoning Overlay / Special Use Permit | Since Sep 2026 · no end date |
| City of St. Peters, MO1-yr data center moratorium | City / Town | Moratorium | May 2026 → May 2027 |
| Jackson County, MO6-mo data center moratorium | County / Parish | Moratorium | Jun 2026 → Dec 2026 |
| Marion County, MO1-yr data center moratorium | County / Parish | Moratorium | Jun 2026 → Jun 2027 |
| Nodaway County, MO6-mo data center moratorium | County / Parish | Moratorium | Jul 2026 → Jan 2027 |
| Palmyra, MOdata center moratorium | City / Town | Moratorium | Since Sep 2026 · no end date |
| Pettis County, MOdata center moratorium | County / Parish | Moratorium | Since Oct 2026 · no end date |
| St. Charles County, MO6-mo data center moratorium | County / Parish | Moratorium | Jul 2026 → Jan 2027 |
| Webster County, MO6-mo data center moratorium | County / Parish | Moratorium | Jun 2026 → Dec 2026 |
Other states
- Texas240
- Virginia201
- California109
- Ohio86
- Georgia80
- Pennsylvania70
- Illinois66
- Arizona55
- Utah52
- New Jersey50
- New York50
- North Carolina39
- Florida38
- Nevada37
- Washington37
- Oklahoma31
- Colorado29
- Iowa25
- Minnesota25
- North Dakota25
- Oregon23
- Tennessee22
- Wisconsin20
- Kansas19