Data centers in North Carolina

27 projects tracked, 3 under construction, with 33 restrictions in force. Updated 2026-09-07.

Projects tracked2724 not cancelled or on hold
Under construction3or partially operational
IT load tracked1,526MWsum of disclosed critical IT load
Restrictions in force33see the ledger below

Every North Carolina project we track

Sorted by IT load. A blank capacity means the figure has not been disclosed, not that the project is small.

ProjectLocation IT loadStatusDeveloperTarget onlineSource
Kingsboro Data Center CampusDC-NC-0027 Edgecombe Co. 900MW Cancelled Energy Storage Solutions
Digital Realty Charlotte CampusDC-NC-0017 Charlotte 400MW Announced Digital Realty
New Hill Digital CampusDC-NC-0028 Apex 300MW Cancelled Natelli Communities
WhiteFiber NC-1 — MadisonDC-NC-0016 Madison 200MW Under Construction WhiteFiber Source ↗
Google Lenoir — Building 3DC-NC-0003 Lenoir 148MW Operational Google 2015
Core Scientific MarbleDC-NC-0005 Marble 117MW Operational Core Scientific 2026
Google Lenoir — Building 4DC-NC-0004 Lenoir 91MW Expansion Google Late 2026
PowerHouse Charlotte — Building 1DC-NC-0018 Charlotte 75MW Announced PowerHouse Data Centers 2027 (phase-in)
PowerHouse Charlotte — Building 2DC-NC-0019 Charlotte 75MW Announced PowerHouse Data Centers 2027 (phase-in)
PowerHouse Charlotte — Building 3DC-NC-0020 Charlotte 75MW Announced PowerHouse Data Centers 2027 (phase-in)
PowerHouse Charlotte — Building 4DC-NC-0021 Charlotte 75MW Announced PowerHouse Data Centers 2027 (phase-in)
Google Lenoir — Building 2DC-NC-0002 Lenoir 72MW Operational Google 2011
Meta Forest City — Building 3DC-NC-0008 Forest City 40MW Operational Meta 2017
Google Lenoir — Building 1DC-NC-0001 Lenoir 39MW Operational Google 2008
Flexential SalisburyDC-NC-0024 Salisbury 36MW Permitting Trammell Crow Company
Meta Forest City — Building 1DC-NC-0006 Forest City 35MW Operational Meta 2012
Meta Forest City — Building 2DC-NC-0007 Forest City 30MW Operational Meta 2013
TierPoint Raleigh Data CenterDC-NC-0010 Raleigh 10MW Operational TierPoint
TierPoint RTP Data CenterDC-NC-0011 Research Triangle Park 8MW Operational TierPoint
Apple Maiden CampusDC-NC-0009 Maiden Operational Apple
AWS Richmond County — Energy Way CampusDC-NC-0012 Richmond Co. Permitting Amazon Web Services Buildout through 2028 Source ↗
Edged Energy Long Ferry Road CampusDC-NC-0023 Rowan Co. Permitting Edged Energy
Microsoft Catawba County — Multi-Campus Program (DCs 2–4)DC-NC-0014 Catawba Co. Announced Microsoft
Microsoft Catawba County — Stover (Hickory)DC-NC-0013 Hickory Under Construction Microsoft
Microsoft Person County MegasiteDC-NC-0015 Woodsdale Township Site Control Microsoft Source ↗
Project DeltaDC-NC-0025 Walnut Cove Permitting Engineered Land Solutions Source ↗
Project Iron SpurDC-NC-0026 Rural Hall On Hold Drox Group LLC Source ↗

By stage

Operational10
Announced6
Permitting4
Cancelled2
Under Construction2
Expansion1
Site Control1
On Hold1

Markets

Restrictions in force in North Carolina

Moratoriums, bans, zoning conditions and tax changes currently in effect. Which specific projects each one reaches is part of the subscription.

JurisdictionLevelWhat it doesWindow
Chatham County, NC1-yr moratorium County / Parish Moratorium Feb 2026 → Feb 2027
City of Asheville, NC1-yr moratorium City / Town Moratorium Jun 2026 → Jun 2027
City of Boiling Spring Lakes, NC1-yr moratorium City / Town Moratorium Jun 2026 → Jun 2027
City of Brevard, NCdata centers limited to industrial districts by conditional rezoning (Ord. 2026-19) City / Town Zoning Overlay / Special Use Permit May 2026 → open-ended
City of Charlotte, NC150-day moratorium City / Town Moratorium Jun 2026 → Nov 2026
City of Durham, NC1-yr moratorium (extended) City / Town Moratorium May 2026 → May 2027
City of Mount Airy, NC60-day data center moratorium City / Town Moratorium Jul 2026 → Sep 2026
City of Wilson, NC1-yr data center moratorium City / Town Moratorium May 2026 → May 2027
Clay County (permanent restriction after earlier crypto moratorium), NCdata center moratorium County / Parish Moratorium Jan 2026 → open-ended
Cumberland County, NC6-mo moratorium County / Parish Moratorium Jun 2026 → Dec 2026
Davie County, NC1-yr moratorium County / Parish Moratorium Jul 2026 → Jul 2027
Durham County, NC1-yr data center moratorium County / Parish Moratorium Jun 2026 → Jun 2027
Gates County, NC1-yr moratorium County / Parish Moratorium Feb 2026 → Feb 2027
Harnett County, NC1-yr moratorium County / Parish Moratorium May 2026 → May 2027
North CarolinaSL 2026-41 electricity tax exemption repeal State Incentive Repeal / Tax Change Jul 2026 → open-ended
Northampton County, NC32-mo moratorium County / Parish Moratorium May 2026 → Jan 2029
Orange County, NC1-yr moratorium County / Parish Moratorium Apr 2026 → Apr 2027
Pasquotank County, NC364-day data center moratorium County / Parish Moratorium May 2026 → May 2027
Rowan County, NC1-yr moratorium County / Parish Moratorium Apr 2026 → Apr 2027
Surry County, NC731-day data center moratorium County / Parish Moratorium Jun 2026 → Jun 2028
Swain County, NC1-yr moratorium County / Parish Moratorium Apr 2026 → Apr 2027
Town of Apex, NC1-yr zoning suspension City / Town Moratorium Apr 2026 → Apr 2027
Town of Bailey, NC300-day data center moratorium City / Town Moratorium May 2026 → Mar 2027
Town of Boone, NC1-yr moratorium City / Town Moratorium Mar 2026 → Mar 2027
Town of Canton, NC1-yr moratorium City / Town Moratorium Feb 2026 → Feb 2027
Town of Clyde, NC1-yr data center moratorium City / Town Moratorium Apr 2026 → Apr 2027
Town of Franklin, NC1-yr moratorium City / Town Moratorium Jul 2026 → Jul 2027
Town of Hillsborough, NC1-yr data center moratorium City / Town Moratorium May 2026 → May 2027
Town of Holly Springs, NC1-yr moratorium City / Town Moratorium Jun 2026 → Jun 2027
Town of Spring Hope, NC1-yr moratorium City / Town Moratorium May 2026 → May 2027
Town of Wendell, NC7-mo moratorium City / Town Moratorium May 2026 → Dec 2026
Town of Woodfin, NC1-yr data center moratorium City / Town Moratorium May 2026 → May 2027
Watauga County, NC1-yr data center moratorium County / Parish Moratorium Apr 2026 → Apr 2027