22 projects tracked, 4 under construction, with 26 restrictions in force. Updated 2026-09-07.

Projects tracked2217 not cancelled or on hold
Under construction4or partially operational
IT load tracked2,262MWsum of disclosed critical IT load
Restrictions in force26see the ledger below

Every Georgia project we track

Sorted by IT load. A blank capacity means the figure has not been disclosed, not that the project is small.

ProjectLocation IT loadStatusDeveloperTarget onlineSource
Stillwater Technology Park — LovejoyDC-GA-0002 Lovejoy 1,200MW Cancelled Stillwater Development Source ↗
Project Sail — Prologis / Atlas Coweta CountyDC-GA-0014 Coweta 900MW Entitled Prologis, Atlas Development Source ↗
Project Peach — CyrusOne PalmettoDC-GA-0015 Palmetto 700MW Entitled CyrusOne, North Coweta Investors, LLC Source ↗
EdgeConneX Union City — Project Steamboat (Microsoft)DC-GA-0012 Union City 324MW Permitting EdgeConneX Phase 1 2026; full build 2029 Source ↗
DataBank Project Indo — CartersvilleDC-GA-0018 Cartersville 200MW Permitting DataBank 2032 (first phase) Source ↗
DC BLOX Atlanta West — DouglasvilleDC-GA-0010 Lithia Springs 120MW Under Construction DC BLOX Expansion as early as 2027 Source ↗
Prime Storage 1155 Powers Ferry Place — MariettaDC-GA-0021 Marietta 18MW Permitting Prime Storage Source ↗
Crow Holdings Highway 85 — Fayetteville (withdrawn)DC-GA-0016 Fayetteville Cancelled Crow Holdings Source ↗
DC BLOX Atlanta East — ConyersDC-GA-0011 Conyers Announced DC BLOX Source ↗
East Village Dothan / EdgeConneX Liberty Road — Villa Rica (denied)DC-GA-0020 Villa Rica Cancelled EdgeConneX Source ↗
Google Columbia County — Pumpkin CenterDC-GA-0005 Columbia Announced Google Source ↗
Google Columbia County — White Oak Technology ParkDC-GA-0004 Appling Announced Google Source ↗
Google LaGrange — Project PegasusDC-GA-0003 LaGrange Under Construction Google Source ↗
Meta Newton Data Center — Stanton SpringsDC-GA-0006 Social Circle Operational Meta Source ↗
Meta Stanton Springs South — Morning HornetDC-GA-0007 Social Circle Under Construction Meta Phase 1 by Dec 31, 2026 Source ↗
Microsoft Douglasville Campus — East US 3DC-GA-0013 Douglasville Under Construction Microsoft 2028 Source ↗
Newton County Technology Park — TPA GroupDC-GA-0008 Covington Permitting TPA Group Source ↗
Oakley Brown Farm Road — Cartersville (withdrawn)DC-GA-0019 Cartersville Cancelled Oakley Real Estate Partners Source ↗
OpenAI Project Camellia — Effingham CountyDC-GA-0001 Rincon Permitting OpenAI 2028–2032 (phased) Source ↗
Project Eisenhower — Eagle South AugustaDC-GA-0009 Augusta Permitting Eagle South LLC, QTS Data Centers Q2 2026 (DCA filing estimate) Source ↗
Project Oak — Newnan (denied)DC-GA-0022 Newnan Cancelled Source ↗
QTS ATL2 East — FayettevilleDC-GA-0017 Fayetteville Permitting QTS Data Centers 2029 Source ↗

By stage

Permitting7
Cancelled5
Under Construction4
Announced3
Entitled2
Operational1

Markets

Restrictions in force in Georgia

Moratoriums, bans, zoning conditions and tax changes currently in effect. Which specific projects each one reaches is part of the subscription.

JurisdictionLevelWhat it doesWindow
Adel (Cook County), GA6-mo data center moratorium City / Town Moratorium Jul 2026 → Jan 2027
Albany, GA1-yr data center moratorium City / Town Moratorium Jul 2026 → Jul 2027
Bulloch County, GA90-day data center moratorium County / Parish Moratorium Feb 2026 → Dec 2026
Calhoun (Gordon County), GAdata center moratorium City / Town Moratorium Jan 2027
Camden County, GA6-mo data center moratorium County / Parish Moratorium May 2026 → Oct 2026
Cedartown, GA6-mo data center moratorium City / Town Moratorium Mar 2026 → Sep 2026
Clayton County, GAdata center moratorium County / Parish Moratorium open-ended
Decatur County, GAdata center moratorium County / Parish Moratorium Apr 2026 → open-ended
DeKalb County, GA100-day data center moratorium County / Parish Moratorium Jun 2025 → Mar 2027
East Point (Fulton County), GA90-day data center moratorium City / Town Moratorium open-ended
Garden City (Chatham County), GA6-mo data center moratorium City / Town Moratorium Jun 2026 → Dec 2026
Gordon County, GAdata center moratorium County / Parish Moratorium Jan 2027
Hart County, GA6-mo data center moratorium County / Parish Moratorium May 2026 → Nov 2026
Kingsland (Camden County), GA1-yr data center moratorium City / Town Moratorium May 2026 → May 2027
Lamar County, GAdata center moratorium County / Parish Moratorium Sep 2025 → open-ended
Lee County, GAdata center moratorium County / Parish Moratorium Dec 2026
Marietta, GAdata center moratorium City / Town Moratorium Jul 2026 → Dec 2026
Milton (Fulton County), GA6-mo data center moratorium City / Town Moratorium Jun 2026 → Dec 2026
Newton County, GAlimited data center application moratorium County / Parish Moratorium Apr 2026 → Oct 2026
Paulding County, GAdata center moratorium County / Parish Moratorium Jul 2026 → Jan 2027
Pike County, GAdata center moratorium County / Parish Moratorium Sep 2025 → open-ended
Rockdale County, GAdata center moratorium County / Parish Moratorium Sep 2026
Roswell, GA90-day data center moratorium City / Town Moratorium Jan 2026 → Sep 2026
South Fulton, GAdata center moratorium City / Town Moratorium Sep 2026
Stephens County, GAdata center moratorium County / Parish Moratorium Oct 2026
Thomas County, GA1-yr data center moratorium County / Parish Moratorium Jan 2026 → Jan 2027