Data centers in Georgia
22 projects tracked, 4 under construction, with 26 restrictions in force. Updated 2026-09-07.
Projects tracked2217 not cancelled or on hold
Under construction4or partially operational
IT load tracked2,262MWsum of disclosed critical IT load
Restrictions in force26see the ledger below
Every Georgia project we track
Sorted by IT load. A blank capacity means the figure has not been disclosed, not that the project is small.
| Project | Location | IT load | Status | Developer | Target online | Source |
|---|---|---|---|---|---|---|
| Stillwater Technology Park — LovejoyDC-GA-0002 | Lovejoy | 1,200MW | Cancelled | Stillwater Development | — | Source ↗ |
| Project Sail — Prologis / Atlas Coweta CountyDC-GA-0014 | Coweta | 900MW | Entitled | Prologis, Atlas Development | — | Source ↗ |
| Project Peach — CyrusOne PalmettoDC-GA-0015 | Palmetto | 700MW | Entitled | CyrusOne, North Coweta Investors, LLC | — | Source ↗ |
| EdgeConneX Union City — Project Steamboat (Microsoft)DC-GA-0012 | Union City | 324MW | Permitting | EdgeConneX | Phase 1 2026; full build 2029 | Source ↗ |
| DataBank Project Indo — CartersvilleDC-GA-0018 | Cartersville | 200MW | Permitting | DataBank | 2032 (first phase) | Source ↗ |
| DC BLOX Atlanta West — DouglasvilleDC-GA-0010 | Lithia Springs | 120MW | Under Construction | DC BLOX | Expansion as early as 2027 | Source ↗ |
| Prime Storage 1155 Powers Ferry Place — MariettaDC-GA-0021 | Marietta | 18MW | Permitting | Prime Storage | — | Source ↗ |
| Crow Holdings Highway 85 — Fayetteville (withdrawn)DC-GA-0016 | Fayetteville | — | Cancelled | Crow Holdings | — | Source ↗ |
| DC BLOX Atlanta East — ConyersDC-GA-0011 | Conyers | — | Announced | DC BLOX | — | Source ↗ |
| East Village Dothan / EdgeConneX Liberty Road — Villa Rica (denied)DC-GA-0020 | Villa Rica | — | Cancelled | EdgeConneX | — | Source ↗ |
| Google Columbia County — Pumpkin CenterDC-GA-0005 | Columbia | — | Announced | — | Source ↗ | |
| Google Columbia County — White Oak Technology ParkDC-GA-0004 | Appling | — | Announced | — | Source ↗ | |
| Google LaGrange — Project PegasusDC-GA-0003 | LaGrange | — | Under Construction | — | Source ↗ | |
| Meta Newton Data Center — Stanton SpringsDC-GA-0006 | Social Circle | — | Operational | Meta | — | Source ↗ |
| Meta Stanton Springs South — Morning HornetDC-GA-0007 | Social Circle | — | Under Construction | Meta | Phase 1 by Dec 31, 2026 | Source ↗ |
| Microsoft Douglasville Campus — East US 3DC-GA-0013 | Douglasville | — | Under Construction | Microsoft | 2028 | Source ↗ |
| Newton County Technology Park — TPA GroupDC-GA-0008 | Covington | — | Permitting | TPA Group | — | Source ↗ |
| Oakley Brown Farm Road — Cartersville (withdrawn)DC-GA-0019 | Cartersville | — | Cancelled | Oakley Real Estate Partners | — | Source ↗ |
| OpenAI Project Camellia — Effingham CountyDC-GA-0001 | Rincon | — | Permitting | OpenAI | 2028–2032 (phased) | Source ↗ |
| Project Eisenhower — Eagle South AugustaDC-GA-0009 | Augusta | — | Permitting | Eagle South LLC, QTS Data Centers | Q2 2026 (DCA filing estimate) | Source ↗ |
| Project Oak — Newnan (denied)DC-GA-0022 | Newnan | — | Cancelled | — | — | Source ↗ |
| QTS ATL2 East — FayettevilleDC-GA-0017 | Fayetteville | — | Permitting | QTS Data Centers | 2029 | Source ↗ |
By stage
Markets
- Atlanta17
- Augusta / CSRA3
- West Georgia (LaGrange)1
- Savannah / Coastal Georgia1
Restrictions in force in Georgia
Moratoriums, bans, zoning conditions and tax changes currently in effect. Which specific projects each one reaches is part of the subscription.
| Jurisdiction | Level | What it does | Window |
|---|---|---|---|
| Adel (Cook County), GA6-mo data center moratorium | City / Town | Moratorium | Jul 2026 → Jan 2027 |
| Albany, GA1-yr data center moratorium | City / Town | Moratorium | Jul 2026 → Jul 2027 |
| Bulloch County, GA90-day data center moratorium | County / Parish | Moratorium | Feb 2026 → Dec 2026 |
| Calhoun (Gordon County), GAdata center moratorium | City / Town | Moratorium | Jan 2027 |
| Camden County, GA6-mo data center moratorium | County / Parish | Moratorium | May 2026 → Oct 2026 |
| Cedartown, GA6-mo data center moratorium | City / Town | Moratorium | Mar 2026 → Sep 2026 |
| Clayton County, GAdata center moratorium | County / Parish | Moratorium | open-ended |
| Decatur County, GAdata center moratorium | County / Parish | Moratorium | Apr 2026 → open-ended |
| DeKalb County, GA100-day data center moratorium | County / Parish | Moratorium | Jun 2025 → Mar 2027 |
| East Point (Fulton County), GA90-day data center moratorium | City / Town | Moratorium | open-ended |
| Garden City (Chatham County), GA6-mo data center moratorium | City / Town | Moratorium | Jun 2026 → Dec 2026 |
| Gordon County, GAdata center moratorium | County / Parish | Moratorium | Jan 2027 |
| Hart County, GA6-mo data center moratorium | County / Parish | Moratorium | May 2026 → Nov 2026 |
| Kingsland (Camden County), GA1-yr data center moratorium | City / Town | Moratorium | May 2026 → May 2027 |
| Lamar County, GAdata center moratorium | County / Parish | Moratorium | Sep 2025 → open-ended |
| Lee County, GAdata center moratorium | County / Parish | Moratorium | Dec 2026 |
| Marietta, GAdata center moratorium | City / Town | Moratorium | Jul 2026 → Dec 2026 |
| Milton (Fulton County), GA6-mo data center moratorium | City / Town | Moratorium | Jun 2026 → Dec 2026 |
| Newton County, GAlimited data center application moratorium | County / Parish | Moratorium | Apr 2026 → Oct 2026 |
| Paulding County, GAdata center moratorium | County / Parish | Moratorium | Jul 2026 → Jan 2027 |
| Pike County, GAdata center moratorium | County / Parish | Moratorium | Sep 2025 → open-ended |
| Rockdale County, GAdata center moratorium | County / Parish | Moratorium | Sep 2026 |
| Roswell, GA90-day data center moratorium | City / Town | Moratorium | Jan 2026 → Sep 2026 |
| South Fulton, GAdata center moratorium | City / Town | Moratorium | Sep 2026 |
| Stephens County, GAdata center moratorium | County / Parish | Moratorium | Oct 2026 |
| Thomas County, GA1-yr data center moratorium | County / Parish | Moratorium | Jan 2026 → Jan 2027 |
Developers and owners active in Georgia
- Atlas Development
- Crow Holdings
- CyrusOne
- DC BLOX
- DataBank
- Eagle South LLC
- EdgeConneX
- Meta
- Microsoft
- North Coweta Investors, LLC
- Oakley Real Estate Partners
- OpenAI
- Prime Storage
- Prologis
- QTS Data Centers
- Stillwater Development
- TPA Group